CSCI 394 Project #3
Date Due: 11/10/14
For this project you are going to do some project
management for your game project. There
are three parts to this assignment.
1. List all the tasks necessary to be done to complete your game
project. Be detailed! Don’t just say “modeling”, say “finish the
level 1 boss model”.
2. Estimate the time it will take to complete each element on the list in
hours and fractions of an hour. Also
list any dependencies that exist among items on the list—for instance, we can’t
begin testing the boss model in the game until the boss model is completed.
3. Develop a Gantt chart for your project. (http://en.wikipedia.org/wiki/Gantt_chart).
This is a project management tool that shows dependencies and estimated time to
completion for each of the tasks, as well as the critical path to completion of
the project, and an estimate of how long completing the entire project will
take.